Who does this Act apply to?
The Act applies to a construction contract in Queensland
entered into on or after the 1st October 2004.
The Act applies to all construction work including the
provision of goods and services related to the
construction contract.
The
Act does not apply to;
-
A construction contract which forms part of a loan
agreement, contract of guarantee or a contract of
insurance under which a recognised financial institution
undertakes to lend money, to guarantee payment or
provide indemnity relating to the construction contract.
-
A construction contract carried out for a resident owner
as defined by the Domestic Contracts Act 2000,
who is a party to the contract.
-
A construction contract where the consideration payable
is calculated in reference to the value of the work
carried out or the value of the goods and services
supplied.
-
Employees of a company
-
Provisions where the party has undertaken the work as
part of a loan agreement.
Am I able to withhold money until I am paid under
another contract?
You are not able to withhold
money due to the claimant until you are paid under another
contract. This is deemed a "pay when paid" provision and
has no effect in relation to any claim for construction
work made under the
Building and Construction
Industry Payments Act.
What must a valid payment claim include?
A "payment
claim" is terminology used in the Act to describe what
would normally be called a tax invoice, progress claim,
final claim etc.
The payment claim must
identify the construction work or related goods and
services to which the progress payment relates. It must
state the amount of the progress payment that the claimant
is claiming and must state
"This payment claim is made
under the Building and Construction Industry Payments
Act".
What should I include in my payment schedule?
When the respondent receives the payment claim from the
claimant they should serve a payment schedule on the
claimant within 10 business days of receiving the payment
claim. The payment schedule must identify the payment
claim to which it relates and must state the amount of the
payment, if any, that the respondent proposes to make.
If the scheduled amount is less than the claimed amount,
the respondent must state reasons why the scheduled amount
is less than the claimed amount.
What should I do, if I do not agree with the payment
claim?
If you do not agree with the payment claim then you must
provide a payment schedule within 10 business days of
receiving the payment claim. The payment schedule must
identify the payment claim to which it relates and must
indicate the amount of the payment that the respondent
proposes to make. If the scheduled amount is less than the
claimed amount, you must identify the reasons why the
scheduled amount is less. It is important to include all
of the reasons as they cannot be introduced later in the
adjudication response.
What happens if I do not serve a payment schedule?
If you do not provide a payment schedule then you will
loose the opportunity to provide an adjudication response.
It is important that if you have valid reasons for
withholding payment that you provide a payment schedule as
this is your opportunity to have your say in the process.
What should I do, if I am served with an Adjudication
Application?
If you are served with an Adjudication Application you
will be required to prepare an Adjudication Response. It
is suggested that you contact the ANA or seek independent
advice should you be served with an Adjudication
Application. Please remember an adjudication response must
be served within 5 business days after receiving a
copy of the application OR 2 business days after
receiving notice of an adjudicator's acceptance of the
application, whichever time expires later.
What should I include in my Adjudication Response?
The adjudication response must be in writing and must
identify the adjudication application to which it relates.
The respondent may provide the adjudicator with an
adjudication response only if the respondent has served a
payment schedule on the claimant within 10 business days
of receiving the payment claim or 5 business days of
receiving the section 21 Notice.
How long will it take for the Adjudicator to make a
decision?
The Adjudicator must make a decision within 10 business
days after the Adjudication response is due or should be
due.
If I am found liable, how long do I have to pay the
Adjudicated Amount?
The respondent is required to pay the adjudicated amount 5
business days after the date on which the adjudicator's
decision is served on the respondent or at a later date,
which the adjudicator decides.
Who pays the Adjudication fees and expenses?
It is the policy at Australian Solutions Centre that no
adjudication decision will be released until the
adjudicator's fees are paid. ASC will send a letter to
both parties notifying each party of the fees. Once the
fees are paid by one or both parties, the decision will be
released to both parties. The adjudicator will state who
is liable for the adjudicator's fees in the decision.
Accordingly, if the claimant has paid the fees for the
purposes of release but the decision states that the
claimant and respondent are equally liable for the
adjudicator's fees, the respondent will be required to pay
the claimant their share of the fees within 5 business
days of being served with the decision or at a later date
decided by the adjudicator.
Is the claimant able to suspend work?
The claimant may suspend work under the construction
contract if at least 2 business days have passed since the
claimant has provided notice of intention to do so to be
given to the respondent under section 15,16 or 24.