|
Who does this Act apply to?
The Act applies to written and oral construction
contracts carried out in NSW. The Act applies to all
construction work including the provision of goods
and services related to the construction contract.
The Act does not apply to;
-
Construction contracts forming part of a loan
agreement
-
Construction contract for residential building work
as defined by the Home Building Act 1989
-
Construction contracts where the consideration
payable is calculated otherwise by reference to the
value of the work carried out.
-
Employees as defined
by the
Industrial Relations Act 1996
Am I able to withhold money until I am paid under
another contract?
The respondent is not able to withhold money due to
the claimant until they are paid under another
contract. This is deemed a "pay when paid" provision
and has no effect in relation to any claim for
construction work made under the Building and
Construction Industry Security of Payments Act.
What must a valid
payment claim include?
A "payment claim" is terminology used in the Act to
describe what would normally be called a tax
invoice, progress claim, final claim etc.
The payment claim must identify the construction
work or related goods and service to which the
progress payment relates. It must state the amount
of the progress payment that the claimant is
claiming and must state "This payment claim is
made under the Building and Construction Industry
Security of Payments Act".
Payment Schedule What
should I include in my payment schedule?
When the respondent receives the payment claim from
the claimant they should serve a payment schedule on
the claimant within 10 business days of receiving
the payment claim. The payment schedule must
identify the payment claim to which it relates and
must state the amount of the payment, if any, that
the respondent proposes to make.
If the scheduled amount is less than the claimed
amount, the respondent must state reasons why the
scheduled amount is less than the claimed amount.
What should I do, if I do not agree with the payment
claim?
If you do not agree with the payment claim then you
must provide a payment schedule within 10 business
days of receiving the payment claim. The payment
schedule must identify the payment claim to which it
relates and must indicate the amount of the payment
that the respondent proposes to make. If the
scheduled amount is less than the claimed amount,
you must identify the reasons why the scheduled
amount is less. It is important to include all of
the reasons as they cannot be introduced later in
the adjudication response.
What happens if I do not serve a payment schedule?
If you do not provide a payment schedule then you
will loose the opportunity to provide an
adjudication response. It is important that if you
have valid reasons for withholding payment that you
provide a payment schedule as this is your
opportunity to have your say in the process.
What should I do, if I am served with an
Adjudication Application?
If you are served with an Adjudication Application
you will be required to prepare an Adjudication
Response. It is suggested that you contact the ANA
or seek independent advice should you be served with
an Adjudication Application. Please remember an
adjudication response must be served within 5
business days after receiving a copy of the
application OR 2 business days after receiving
notice of an adjudicator's acceptance of the
application, whichever time expires later.
How long will it take for the Adjudicator to make a
decision?
The Adjudicator must make a determination within 10
business days after the date on which the
Adjudicator notified the parties as to his or her
acceptance of the application or within such further
time as the claimant and respondent may agree. It is
the policy at ASC that the Adjudicator will accept
the application within 4 business days of ASC
receiving the application.
If I am found liable, how long do I have to pay the
Adjudicated Amount?
The respondent is required to pay the adjudicated
amount 5 business days after the date on which the
adjudicator's decision is served on the respondent
or at a later date, which the adjudicator decides.
Who pays the
Adjudication fees and expenses?
The claimant and respondent are jointly and
severally liable to contribute to the payment of the
adjudicator's fees and expenses in equal proportions
or in such proportions as the adjudicator may
determine. The Adjudicator will state in the
determination who is liable to pay the fees.
Initially one or both parties will be required to
pay the Adjudicators fees for the purposes of
release of the determination as it is the policy at
ASC that no determination is released until the
adjudicator's fees have been paid. Once the
determination is released, the party who is liable
will have 5 business days to reimburse the party who
has paid the fees for the purposes of releasing the
determination.
Is the claimant able to suspend work?
make a deter Division 3, section 27 deals with the
claimant's right to suspend work. A claimant may
suspend work under the construction contract if at
least 2 business days have passed since the claimant
has provided the respondent with notice of intention
to suspend work under section 15, 16 or 24.
If assistance or further information is required
please contact us on 1300 722 624.
|