|
The industry has continually experienced frustration
and sometimes anger at only being paid a portion of
the rightful entitlement or worse still not being paid
at all. When confronted with this scenario the only
way forward was to agree to a lesser amount or be faced
with the prospect of an even more frustrating contractual
or legal challenge that consumes time and money at an
alarming rate with little hope of a satisfactory outcome.
This Act introduces a process where if a payment dispute
arises the Claimant can make an adjudication application
and receive an Adjudicator’s determination in
a fast and efficient manner. If the Claimant’s
case and submission is commendable and success follows
the Respondent must pay the adjudicated amount to the
Claimant. It then becomes the Respondent’s decision
whether to pursue other contractual or legal challenges
through alternate processes. This in effect places the
Respondent in the same position as the Claimant in the
above-mentioned scenario. The roles have reversed.
Cash flow forms the financial basis of the building
and construction industry, in time this Act will change
the payment culture of the building and construction
industry resulting in cash being distributed in a far
more equitable manner.
The Act applies to all construction contracts in Victoria
entered into on or after the 31st January 2003. The
Act applies to all construction work including goods
and services related to the construction contract. If
required the Act can also provide a far more streamlined
path through the court system.
The Act does not override contract conditions other
than providing an independent adjudication process for
disputed payment claims, bans "paid when paid"
clauses and permits the suspension of work for non-payment.
The four main players in the Act are as follows:
-
Claimant - the party making the payment
claim.
-
Respondent - the party receiving the
payment claim.
-
Authorised Nominating Authority (ANA)
- a body appointed by the Minister.
-
Adjudicator - a "natural person"
not a party to the Contract.
The four main documents involved in the Act are as follows:
-
Payment Claim - is a tax invoice, progress
claim, final claim, etc and is provided by the Claimant.
(Claimant)
-
Payment Schedule – is a response
to the payment claim and is provided by the Respondent.
(Respondent)
-
Adjudication Application – is
an application made to an ANA by the Claimant. (Download
PDF
or Download
Word)
-
Adjudication Response – is a
response to the adjudication application and is made
by the Respondent. (Download
PDF
or Download
Word)
If assistance or further information is required please
contact us on 1300 722 624
|