VICTORIA • Claimant - Building and Construction Industry Security of Payment Act

The Claimant is the party making the "payment claim".

Under the Act the Claimant has a specific role and has only two (2) documents to manage. They are as follows:

Payment Claim

A "payment claim" is terminology used in the Act to describe what would normally be called a tax invoice, progress claim, final claim, etc.

It is better that only one payment claim is submitted per construction contract per period stated in the contract (week, fortnight, 25th of month, etc) or if nothing stated in the contract then after the last day of each month.

For a "payment claim" to be subject to the Act the payment claim must state somewhere on the document "This payment claim is made under the Building and Construction Industry Security of Payment Act". A computer driven system should enable these words to be a standard entry on all payment claims produced. If a manual system is used a rubber stamp or similar will be sufficient.

A payment claim is the document that initiates the entire process. A payment claim must identify the construction work to which the payment claim relates and must indicate the amount that the Claimant claims to be due.

It is important for the Claimant to ensure that the payment claim meets all requirements of the contract and the Act. A payment claim must be valid under the Act and correct service is paramount.

We recommend that "first time" Claimants or those Claimants that are not comfortable with the process should seek assistance and or further information prior to serving a payment claim.

Adjudication Application

An "adjudication application" is a document prepared by the Claimant in support of the Claimant’s case for being paid.

If the Respondent provides a payment schedule showing an amount the Respondent proposes to pay
(Respondent) that is not acceptable to the Claimant or fails to pay the scheduled or claimed amount the Claimant may elect to make an adjudication application.

An adjudication application is the opportunity for the Claimant to make a submission to the Adjudicator
(Adjudicator) in support of the Claimant’s case for being paid.

The adjudication application is made to an Authorised Nominating Authority (ANA) of the Claimant’s choice with a copy being sent to the Respondent at the same time.

The issue of timing and process associated with an adjudication application is one of the more complex sections of the Act. In general terms an adjudication application must be made within 5 business days after receiving a payment schedule.

The adjudication application must be in writing, must state that it is made under the Act, must identify the payment claim and payment schedule to which it relates and should include all submissions and documents in support of the Claimant’s case.

The adjudication application is an important document for the Claimant and requires careful consideration and preparation prior to submission.

The adjudication application should address the reasons, if any, the Respondent has provided for withholding payment. If this document is not correct or of poor quality the Claimant’s chances of success in an Adjudication Application is significantly reduced.

We recommend that "first time" Claimants or those Claimants that are not comfortable with the process should seek assistance and or further information 10 business days after the Claimant has served the payment claim.

If assistance or further information is required please contact us on 1300 722 624

 
 