|
Am I able to apply for
Adjudication?
You will be eligible to apply for adjudication under the
Building and Construction Industry Payments Act 2004 if
you have entered into a construction contract after the 1
October 2004.
-
The contract may be written or oral or partly written and
partly oral.
-
The contract must have been carried out in Queensland
-
Construction work including provision of goods and
services related to the construction contract.
The Act does not apply to;
-
A construction contract which forms part of a loan
agreement, contract of guarantee or a contract of
insurance under which a recognised financial institution
undertakes to lend money, to guarantee payment or provide
indemnity relating to the construction contract.
-
A construction contract carried out for a resident owner
as defined by the Domestic Contracts Act 2000, who is a
party to the contract.
-
A construction contract where the consideration payable is
calculated in reference to the value of the work carried
out or the value of the goods and services supplied.
-
Employees of a company.
When am I able to submit
my payment claim?
You are able to submit your payment claim on the date
stated in the contract or if the contract does not provide
a reference date the last day of the named month in
which the construction work was first carried out or the
related goods and services were supplied under the
contract.
What is a payment claim?
A "payment
claim" is terminology used in the Act to describe what
would normally be called a tax invoice, progress claim,
final claim etc.
The payment
claim must identify the construction work or related goods
and services to which the progress payment relates. It
must state the amount of the progress payment that the
claimant is claiming and must state "This payment claim
is made under the Building and Construction Industry
Payments Act".
When is the due date for
payment?
The due date for payment will be in accordance with your
contract however if there is no payment term provisions in
your contract the due date for payment will be 10 business
days after the payment claim is made pursuant to Section
15.
Am I able to obtain
interest on overdue payments?
Interest can be obtained on overdue payments.
The Adjudicator will award interest on the unpaid amount
at the greater of the following rates;
-
The rate prescribed under the Supreme Court Act 1995,
section 48(1) for debts under a judgement or order; or
-
the rate specified under the contract.
Section 15
(3) For a construction contract to
which Queensland Building Services Authority Act 1991,
section 67P applies because it is a building contract,
interest is payable at the penalty rate under that
section.
Is the respondent able
to withhold payment until he receives payment under
another contract?
In accordance with section 16 the respondent is not able
to withhold payment until he receives payment under
another contract. This is deemed a "pay when paid"
provision and is therefore void.
What is a payment
schedule?
When the respondent receives the payment claim from the
claimant they should serve a payment schedule on the
claimant within 10 business days of receiving the payment
claim. The payment schedule must identify the payment
claim to which it relates and must state the amount of the
payment, if any, that the respondent proposes to make.
If the scheduled amount is less than the claimed amount,
the respondent must state the reasons why the scheduled
amount is less than the claimed amount.
The Respondent has not
provided a payment schedule, what is my next step?
If the respondent does not provide a payment schedule, the
claimant is entitled to believe that the respondent will
pay the claimed amount by the due date for payment.
However, once the due date for payment lapses and no
payment has been received the claimant may recover the
amount as a debt owing in any court of competent
jurisdiction or take steps to apply for adjudication. If
the claimant elects to apply for adjudication, the
claimant must send out the appropriate 5 day notice under
section 21 notifying the respondent of their intention to
proceed with adjudication.
I have received a
payment schedule but the Respondent has not paid me in
accordance with the payment schedule?
If the respondent has not paid you in accordance with the
payment schedule you may recover the unpaid amount as a
debt owing in any court of competent jurisdiction or make
an adjudication application under section 21(1)(a)(ii) in
relation to the payment claim.
When must I submit the
Adjudication Application?
-
Where the respondent has provided a payment schedule
which you do not agree with, you will be required to
submit your application to the ANA within 10 business
days of receiving the payment schedule.
-
Where you have received a payment schedule and the
respondent has failed to pay the whole or any part of
the scheduled amount to the claimant by the due date
for the payment, the claimant must submit their
application within 20 business days after the due date
for payment.
-
Where you have not received a payment schedule, your
application will be due at the end of the 5 day period
referred to in subsection 21(2)(b).
Who must I submit my
application to?
The claimant is required to submit the adjudication
application to an Authorised Nominating Authority.
Australian Solutions Centre is an Authorised Nominating
Authority.
How long will I need to
wait before a decision is made?
The Adjudicator must make a decision within 10 business
days after the Adjudication response is due or should be
due.
How is the Adjudicator
appointed?
When
ASC receives an Adjudication application, a case manager
is appointed. The case manager will be the point of
contact for both the claimant and respondent. The case
manager will manage the case from start to finish and will
be able to answer any of your questions regarding the
process.
The
Case Manager will determine which adjudicator would be
best suited to decide the adjudication application.
The
process of selecting the appropriate adjudicator will have
regard for the following:
Two
adjudicators will be selected - a 'primary' adjudicator
and one 'reserve' adjudicator. Both the primary and
reserve adjudicators will be contacted by the Case
Manager. If the 'primary' adjudicator cannot accept the
nomination then the 'reserve' adjudicator will be
nominated immediately.
To
ensure that issues of probity are maintained, prior to
nomination there will be a requirement for each
adjudicator to declare the following: They have the
qualifications, expertise and experience necessary to
competently carry out the adjudication in accordance with
the Act;
-
They
have the qualifications, expertise and experience
necessary to competently carry out the adjudication in
accordance with the Act;
-
They
are not a party to the contract;
-
They
will at all times act in accordance with the ASC Code of
Conduct; and
-
They
consider they have no conflict of interest in adjudicating
this application.
What will the
Adjudicator decide?
The Adjudicator will decide the amount of the progress
payment if any to be paid by the respondent to the
claimant, the date on which any amount became or becomes
payable and the rate of interest payable on any amount.
The decision will be in writing and will include reasons
for the decision unless the claimant and respondent have
both asked the adjudicator not to include the reasons in
the decision.
In deciding the application, the adjudicator is to
consider the following matters only;
-
The provisions of the Act
-
The construction contract whether written or oral
-
The payment claim together with all submissions properly
made by the claimant in support of the claim
-
The payment schedule, if any, together with all
submissions properly made by the respondent in support of
the schedule;
-
The results of any inspection carried out by the
adjudicator of any matters to which the claim relates.
If I am successful, when
is the Respondent required to pay?
The respondent is required to pay the adjudicated amount 5
business days after the date on which the adjudicator's
decision is served on the respondent or at a later date
which the adjudicator decides.
What happens if the
Respondent does not pay the Adjudicated amount?
If the respondent fails to pay the adjudicated amount, the
claimant is able to request an adjudication certificate
from the authorised nomination authority, which can then
be filed in a court of competent jurisdiction, as a
judgment for debt.
When am I able to
request an Adjudication certificate?
An adjudication certificate can be requested by the
claimant if the respondent does not pay the adjudicated
amount 5 business days after the date on which the
adjudicator's decision is served on the respondent or at a
later date on which the adjudicator decides.
What do I do with the
Adjudication certificate?
See adjudication certificates
Who pays the
Adjudication fees?
It is the policy at Australian Solutions Centre that no
adjudication decision will be released until the
adjudicator's fees are paid. ASC will send a letter to
both parties notifying each party of the fees. Once the
fees are paid by one or both parties, the decision will be
released to both parties. The adjudicator will state who
is liable for the adjudicator's fees in the decision.
Accordingly, if the claimant has paid the fees for the
purposes of release but the decision states that the
claimant and respondent are equally liable for the
adjudicator's fees, the respondent will be required to pay
the claimant their share of the fees within 5 business
days of being served with the decision or at a later date
decided by the adjudicator.
If assistance or further information is required please
contact us on 1300 722 624 |