|
Overview
of Amendments to the Victorian Security of Payments
Legislation
The Victorian Building and Construction Industry
Security of Payment Act 2002 was introduced in January
2003 to protect the rights of subcontractors who are
being denied their right to payment.
In July of this year, a Bill was passed which
will come into effect in early 2007, making significant
changes to the current legislation. A commencement date
is yet to be set, however, Australian Solutions Centre
will keep you updated as information is released.
"The
main purpose of this bill is to amend the Building and
Construction Industry Security of Payment Act 2002 to
make it more effective in enabling any person who
carries out building or construction work to promptly
recover progress payments."
(Mr.
Hulls, Building and Construction Industry Security of
Payment (Amendment) Bill - Second Reading Speech -
VIC Hansard).
The
new amendments recognise the need for improvements to
the current Act. The
new amendments will build on the current legislation by
not only improving the existing provisions but also
introducing new features to protect the rights of
subcontractors in recovering outstanding payments.
Claimants will now have the option of applying for
Adjudication, as opposed to enforcing payment in a court
or tribunal, which can be expensive and time-consuming.
OVERVIEW
OF THE AMENDMENTS
Entitlement
to a wider range of payments
Claimants will now be able to seek Adjudication
for a wider range of payments including;
Submission
of Payment Claims
A payment claim must be submitted within three
months from the reference date, for payment of each item
of work carried out or goods provided, or such longer
period as the contract may provide.
Claimable
Variations
In regards to variations, claimants will only be
entitled to include "claimable variations" when
calculating the progress payment. There will be two
classes of claimable variations. The first class
includes agreed variations. The second class of
variations is a variation where the work is completed
and the respondent requested the work to be done, but
the parties do not agree on the following;
-
that the work is a variation,
-
the claimants entitlement to payment,
-
the value of the work,
-
method of valuing and/or
-
time for payment.
Any matters that the Adjudicator determines
but which are not considered 'claimable variations'
will be deemed void and will have no effect. However,
matters in the determination, which are within the power
of the Adjudicator, will remain effective.
Excluded
Amounts
Claimants will not be entitled to claim
'Excluded Amounts'. Excluded amounts include amounts
that are not claimable variations, damages, delay costs,
latent conditions, and changes in regulatory
requirements.
Payment
Schedules
Claimants may now apply for Adjudication even
though the respondent has not provided a payment
schedule. However, the claimant must notify the
respondent within 10 business days of the due date for
payment of the claimant's intention to apply for
adjudication of the payment claim and the respondent has
been provided with the opportunity to provide a payment
schedule to the claimant within 2 business days after
receiving the claimant's notice.
Adjudication
Applications
The new amendments will extend the period within
which an adjudication application can be lodged,
following the issue of a payment schedule from 5 to 10
business days.
Interest
Claimants will have the right to claim interest
from the date that the payment first becomes due.
Lien
in respect of unpaid progress payment
The legislative changes will introduce the right
to exercise a statutory lien or a right over unfixed
goods to the value of the unpaid amount. This provision
is subject to any pre-existing rights over the goods
such as where the client has already paid for them.
Pay
when paid provisions
Any provisions within a contract, which makes
liability to pay money owing, or the due date for
payment of money owing, contingent or dependant on the
operation of another will be invalid.
Adjudication
Responses
The Respondent has the right to lodge an
adjudication response however should the adjudication
response include reasons for withholding payment that
were not included in the payment schedule, the claimant
will have the opportunity to provide a response to those
reasons within 2 business days of being served with
those reasons by the adjudicator.
Appointment
of Adjudicator
An Authorised Nominating Authority must make
appointment of an Adjudicator. Parties will no longer be
entitled to select and agree on an Adjudicator.
Review
of Adjudication
A review process will be introduced for aggrieved
parties to seek review of an adjudication determination
however this will only be available in limited
circumstances including; the adjudicated amount exceeds
$100,000, a payment schedule has been provided, the
Adjudicated amount includes an excluded amount and the
excluded amount has been identified in the payment
schedule or the Adjudication response.
An application for review can only be made by the
respondent after the Respondent has paid the Adjudicated
amount to the claimant excluding the alleged excluded
amounts. The excluded amounts must also be paid into a
designated trust account.
Adjudication
Certificates & Consequences of
When a respondent does not pay the adjudicated
amount by the due date for payment, the claimant will be
able to request an adjudication certificate from the
Authorised Nominating Authority, lodge this certificate
with the court and recover the money as a debt due. This
process is more cost effective and less time consuming
then a court hearing.
The current legislation allows respondents
to provide security of payment such as placing the money
into a trust fund. The bill removes this provision
making the respondent pay the adjudicated amount.
Suspension
of Work
The bill introduces restrictions on the right to
suspend work when payment is not made by the due date.
Claimants will be required to return to work promptly
after payment is made to
minimise unnecessary delays to work on site. The bill
will provide claimants with protection against any
liability for losses resulting from the suspension of
works.
Subcontractors will be able to use the
adjudication process to access amounts clients or head
contractors hold on trust for subcontractors until works
are completed.
We will keep you updated !
If assistance or further information is required
please contact us on 1300 722 624 |