|
Who is the Adjudicator?
A person may be an adjudicator in relation to a
construction contract if registered as an adjudicator
under this Act. A person cannot be appointed as an
Adjudicator if the person is a party to the contract.
ASC Adjudicators and Areas
of Expertise
ASC currently maintains a
small panel of trained adjudicators under the Queensland
Act. We believe that a small panel is beneficial as it
allows all of our adjudicators to adjudicate on more
matters which means greater experience and a greater
knowledge of the Act and the issues arising. A brief
overview of the background and experience is provided
below:
-
Contract Law Specialists
-
Business Development Management
-
Building & Construction Law
-
Arbitration and Dispute Resolution
-
Practising Lawyers
-
Graded Commercial Arbitrators
-
Accredited Construction Adjudicator (Academy of
Construction Adjudicators, London UK)
-
Bachelor of Engineering
-
Practising Civil Engineers
-
Electrical
-
Building
-
Plumbing
-
Trainer of Construction Adjudicators (NSW and VIC Acts)
-
Trainer of Project and Contract Management Training
Courses
The Role of the Adjudicator
The Adjudicator is the person who makes the adjudication
decision. The decision will be in writing and includes
reasons for the decision.
The Adjudicator will decide;
-
Amount of the progress payment, if any, to be paid by
the respondent to the claimant;
-
Date on which the amount became or becomes payable; and
-
Rate of interest payable on any amount.
The adjudicator is to consider the following matters only;
-
Provisions of this Act
-
The construction contract
-
Payment claim and all submissions properly made by the
respondent in support of the claim
-
Payment schedule, if any, together with all submissions
that have been properly made by the respondent in
support of the schedule;
-
Results of any inspection carried out by the adjudicator
of any matter to which the claim relates.
How is the Adjudicator paid?
It is the policy at Australian Solutions Centre that no
adjudication decision will be released until the
adjudicator's fees are paid. ASC will send a letter to
both parties notifying each party of the fees. Once the
fees are paid by one or both parties, the decision will be
released to both parties. The adjudicator will state who
is liable for the adjudicator's fees in the decision.
Accordingly, if the claimant has paid the fees for the
purposes of release but the decision states that the
claimant and respondent are equally liable for the
adjudicator's fees, the respondent will be required to pay
the claimant their share of the fees within 5 business
days of being served with the decision or at a later date
decided by the adjudicator.
How is the Adjudicator
appointed?
ASC does not appoint
adjudicators on a rotary basis, meaning we do not appoint
the next in line. At ASC we appoint the adjudicator who we
believe is the best person to adjudicate your matter. We
believe that this ensures fair and just outcomes for both
the claimant and respondent.
When
ASC receives an Adjudication application, a case manager
is appointed. The case manager will be the point of
contact for both the claimant and respondent. The case
manager will manage the case from start to finish and will
be able to answer any of your questions regarding the
process.
The
Case Manager will determine which adjudicator would be
best suited to decide the adjudication application.
The
process of selecting the appropriate adjudicator will have
regard for the following:
-
The
Case Manager will read through the application to
ascertain the nature of non-payment for the dispute ie
technical issues, legal issues or general contract
issues.
-
Based
on the information ascertained the adjudicator will be
chosen based on their relevant background, area of
expertise and experience.
Two
adjudicators will be selected - a 'primary' adjudicator
and one 'reserve' adjudicator. Both the primary and
reserve adjudicators will be contacted by the Case
Manager. If the 'primary' adjudicator cannot accept the
nomination then the 'reserve' adjudicator will be
nominated immediately.
To
ensure that issues of probity are maintained, prior to
nomination there is a requirement for each adjudicator to
declare the following:
-
They
have the qualifications, expertise and experience
necessary to competently carry out the adjudication in
accordance with the Act;
-
They
are not a party to the contract;
-
They
will at all times act in accordance with the ASC Code of
Conduct; and
-
They
consider they have no conflict of interest in
adjudicating this application.
If assistance or further information is required
please contact us on 1300 722 624 |